CDOT · Transportation
I-70 Floyd Hill Improvement Project
Westbound third lane, new canyon viaduct & interchange rebuild (8 mi, Clear Creek County). Timeline 2023–2029.
Updated Sep 25
Copy this address:
CALC Up 29.3% from $700M in 2020.
Formula: ($905M − $700M) ÷ $700M. First figure: 2020 CDOT estimate.
Underway. What this stage means
Underway. The main work on this project started. Money goes out as the work goes on.
The stages, in order
- Requested An agency asked. No money yet.
- Funded Money approved. Work still to start.
- Underway Work started. Money goes out. This project
- Complete Work complete.
Halted Work stopped before the end.
This stage is our reading of the sources at the foot of this page, last read 31 October 2026.
Timeline 2023–2029
CDOT’s dashboards print a paid figure for four of this project’s five contracts. Our sum: $62.04M + $55.27M + $106.52M + $43.86M = $267.69M. CDOT prints no total. Who is being paid, contract by contract
Your take on this project
A rating here is not a vote, a scientific poll or a message to your representative.
Your rating is kept with no name, and it is never published on this site.
How we use this
Latest public update
CDOT's 2025 cost-to-deliver estimate is $905M, up from the 2020 estimate of $700M, citing construction and material costs. CDOT's monthly accountability dashboards cover the project's four construction contracts. They show $267.69M paid to the contractor by June 2026, against $678.15M in current contract value (our sums of the four contracts' figures). The fifth contract listed, for design, is not in those sums. June 2026 is the newest month all four dashboards report, as of 31 October 2026; two contracts have later months, which are not added.
Open questions for the state (3)
- What are the specific cost drivers behind the rise from $700M (2020) to $905M (2025)?
- Is the 2026 excavation season on track to hold the westbound 2027 opening?
- CDOT's dashboards for the East and early-access sections stop at June 2026, while the West and Central sections reach August 2026. When will the other two catch up?
Total cost and spending
Total cost & funding are drawn from the official record(s) listed below.
Budget to actual
Public records tie $288,213,509 of payments to this project. That is 31.8% of the $905,000,000 basis: cDOT's 2025 cost to deliver the project as scoped.
- Documented $288,213,509 31.8% of the basis
Each link is graded by how sure the record is. The other $616,786,491 is unlinked. Some of it may be unspent, and some may be paid where no public record names this project.
See every link and its evidenceMilestones (6)
- Design & NEPA complete — 2021
- Construction began — July 2023
- Rock excavation & bridge structures — through 2026
- Westbound new alignment open — end 2027
- Eastbound alignment open — end 2028
- Full completion — 2029
Estimate, first to current
Who is being paid (5)
| Political giving | |||||
|---|---|---|---|---|---|
| Kraemer North AmericaCM/GC contract, East section (project 25174) | $64.13M contract | $62.04M paid · Jun 2026 | A | CDOT project page | Search TRACER |
| Kraemer North AmericaCM/GC contract, West section (project 25175) | $105.23M contract | $55.27M paid · Jun 2026 | A | CDOT project page | Search TRACER |
| Kraemer North AmericaCM/GC contract, Central section (project 25177) | $459.31M contract | $106.52M paid · Jun 2026 | A | CDOT project page | Search TRACER |
| Kraemer North AmericaCM/GC contract, Central section early access (project 25176) | $49.48M contract | $43.86M paid · Jun 2026 | A | CDOT project page | Search TRACER |
| Atkins North America (AtkinsRéalis)Lead design engineer — 6-year design contract (2022) | $31M design | PENDING Not published for this contract. | B | company release / ENR | Search TRACER |
Pacing CALC
Is the money keeping pace with the calendar?
All 4 contracts together, June 2026
▼ −7.9 percentage points, paid behind the calendar
Paid 39.5% of the combined contract value with 47.4% of the time used, weighted by value: 7.9 percentage points behind an even pace, $53.55M less.
An even pace is our baseline, not CDOT's plan. A gap is a question to ask, not a verdict, and it compares money with time, not with the work done.
See the spending, month by monthMoney paid against contract time used, from CDOT's monthly dashboards, the latest each contract has.
- East section, June 2026 Paid 96.7% of the contract with 97.4% of its time used: 0.6 percentage points behind an even pace, $0.40M less.
- West section, August 2026 Paid 55.8% of the contract with 57.2% of its time used: 1.4 percentage points behind an even pace, $1.49M less.
- Central section, early access, June 2026 Paid 88.6% of the contract with 97.6% of its time used: 9.0 percentage points behind an even pace, $4.44M less.
- Central section, August 2026 Paid 26.9% of the contract with 37.7% of its time used: 10.8 percentage points behind an even pace, $49.68M less.
Figures in CDOT’s dashboards that do not add up
These are CDOT’s own figures, shown exactly as CDOT printed them, and we do not say which one is right.
-
Does not add up CALC
I-70 Floyd Hill West Section, July 2024
CDOT’s dashboard for this month prints:
- Payments to date: $67.48 Million
- Design Payments remaining: $94.79 Million
- Current Contract Value: $102.26 Million
Paid plus remaining comes to $162.27M, which is $60.01M more than the current contract value.
$67.48M + $94.79M = $162.27M; $162.27M − $102.26M = $60.01MCDOT’s dashboard, July 2024 (PDF) (opens in a new tab) · read 25 September 2026
-
Change orders do not add up CALC
I-70 Floyd Hill West Section, February 2026
CDOT’s dashboard for this month prints:
- Original Contract Amount (chart label): 102.26 Million
- Total Change Orders to Date: $0
- Current Contract Value: 105.23 Million
Those two add up to $102,260,000.00. That is $2,970,000.00 less than the current value.
$102.26M + $0.00 = $102,260,000.00; $105.23M − $102,260,000.00 = $2,970,000.00CDOT’s dashboard, February 2026 (PDF) (opens in a new tab) · read 25 September 2026
-
Change orders do not add up CALC
I-70 Floyd Hill West Section, March 2026
CDOT’s dashboard for this month prints:
- Original Contract Amount (chart label): 102.26 Million
- Total Change Orders to Date: $0
- Current Contract Value: 105.23 Million
Those two add up to $102,260,000.00. That is $2,970,000.00 less than the current value.
$102.26M + $0.00 = $102,260,000.00; $105.23M − $102,260,000.00 = $2,970,000.00CDOT’s dashboard, March 2026 (PDF) (opens in a new tab) · read 25 September 2026
-
Change orders do not add up CALC
I-70 Floyd Hill West Section, April 2026
CDOT’s dashboard for this month prints:
- Original Contract Amount (chart label): 102.26 Million
- Total Change Orders to Date: $0
- Current Contract Value: 105.23 Million
Those two add up to $102,260,000.00. That is $2,970,000.00 less than the current value.
$102.26M + $0.00 = $102,260,000.00; $105.23M − $102,260,000.00 = $2,970,000.00CDOT’s dashboard, April 2026 (PDF) (opens in a new tab) · read 25 September 2026
-
Change orders do not add up CALC
I-70 Floyd Hill West Section, May 2026
CDOT’s dashboard for this month prints:
- Original Contract Amount (chart label): 102.26 Million
- Total Change Orders to Date: $0
- Current Contract Value: 105.26 Million
Those two add up to $102,260,000.00. That is $3,000,000.00 less than the current value.
$102.26M + $0.00 = $102,260,000.00; $105.26M − $102,260,000.00 = $3,000,000.00CDOT’s dashboard, May 2026 (PDF) (opens in a new tab) · read 31 October 2026
-
Change orders do not add up CALC
I-70 Floyd Hill West Section, June 2026
CDOT’s dashboard for this month prints:
- Initial Contract Value: $102.26 Million
- Total Change Orders to Date: $0
- Current Contract Value: 105.23 Million
Those two add up to $102,260,000.00. That is $2,970,000.00 less than the current value.
$102.26M + $0.00 = $102,260,000.00; $105.23M − $102,260,000.00 = $2,970,000.00CDOT’s dashboard, June 2026 (PDF) (opens in a new tab) · read 31 October 2026
-
More than one document claims one month FACT
Central section (project 25177), June 2024
Three different CDOT documents are each dated June 2024 for this contract, and they print different figures:
-
Linked as “June 2024” and “June 2025” (PDF) (opens in a new tab), dated “June 2024”, read 25 September 2026
- Design Payments to date: $18.31 Million
- Payments remaining: $8.42 Million
- Current Design Contract Value: $26.73 Million
-
Linked as “July 2024” (PDF) (opens in a new tab), dated “June 2024”, read 25 September 2026
- Design Payments to date: $18.85 Million
- Payments remaining: $7.89 Million
- Current Design Contract Value: $26.73 Million
-
Linked as “August 2024” (PDF) (opens in a new tab), dated “June 2024”, read 25 September 2026
- Design Payments to date: $19.52 Million
- Payments remaining: $7.22 Million
- Current Design Contract Value: $26.73 Million
-
-
More than one document claims one month FACT
East section (project 25174), July 2024
Two different CDOT documents are each dated July 2024 for this contract, and they print different figures:
-
Linked as “July 2024” (PDF) (opens in a new tab), dated “July 2024”, read 25 September 2026
- Payments to date: $32.43 Million
- Payments remaining: $31.70 Million
- Current Contract Value: $64.13 Million
-
Linked as “August 2024” (PDF) (opens in a new tab), dated “July 2024”, read 25 September 2026
- Payments to date: $35.94 Million
- Payments remaining: $28.19 Million
- Current Contract Value: $64.13 Million
-
-
Link names a different month FACT
I-70 Floyd Hill Central Section
CDOT’s dashboards page links this document as “June 2025”. The document itself is dated “June 2024”.
The document (PDF) (opens in a new tab) · CDOT’s dashboards page (opens in a new tab) · read 25 September 2026
-
Link names a different month FACT
I-70 Floyd Hill Central Section
CDOT’s dashboards page links this document as “July 2024”. The document itself is dated “June 2024”.
The document (PDF) (opens in a new tab) · CDOT’s dashboards page (opens in a new tab) · read 25 September 2026
-
Link names a different month FACT
I-70 Floyd Hill Central Section
CDOT’s dashboards page links this document as “August 2024”. The document itself is dated “June 2024”.
The document (PDF) (opens in a new tab) · CDOT’s dashboards page (opens in a new tab) · read 25 September 2026
-
Link names a different month FACT
I-70 Floyd Hill East Section
CDOT’s dashboards page links this document as “August 2024”. The document itself is dated “July 2024”.
The document (PDF) (opens in a new tab) · CDOT’s dashboards page (opens in a new tab) · read 25 September 2026
-
Link names a different month FACT
I-70 Floyd Hill West Section
CDOT’s dashboards page links this document as “August 2024”. The document itself is dated “July 2024”.
The document (PDF) (opens in a new tab) · CDOT’s dashboards page (opens in a new tab) · read 25 September 2026
-
Link names a different month FACT
I-70 Floyd Hill West Section
CDOT’s dashboards page links this document as “November 2025”. The document itself is dated “October 2025”.
The document (PDF) (opens in a new tab) · CDOT’s dashboards page (opens in a new tab) · read 25 September 2026
None of these figures is used in a total, a chart or the pacing view on this site.
Sources and receipts (3)
- ACDOT — I-70 Floyd Hill project page: cost, timeline and contractor (codot.gov)read 24 September 2026
- ACDOT — I-70 Floyd Hill monthly contract dashboards: paid to date (June 2026)PENDING no link on fileread 31 October 2026
- BNews coverage of $905M scopePENDING no link on filedated 2025–26