CDOT · Transportation
Vasquez Boulevard Improvements: I-270 to 64th Avenue
Lane, median, signal and intersection work on Vasquez Boulevard in Commerce City, the first of two scheduled construction packages (Adams County). Timeline Jul 2025–Jan 2027.
Copy this address:
Timeline Jul 2025–Jan 2027
CDOT’s dashboard prints this for one contract, not for the whole project. Printed: $7,597,382.84. Who is being paid
Your take on this project
Latest public update
CDOT's project page prints a Construction Cost of $10.9 million for package 1 on Vasquez Boulevard, from mile point 293 to 293.7 in Commerce City, with work from July 2025 to January 2027. CDOT's September 2026 dashboard prints $7,597,382.84 paid to date and $4,824,095.39 remaining on a current contract value of $12,421,478.23. That is the one construction manager/general contractor contract the dashboard reports on, and its value and the page's construction cost are different figures that this site does not add or reconcile. CDOT's page says package 2 was expected to begin in early 2026 and package 3 is on hold until further funding is obtained.
Open questions for the state (2)
- Package 3 is on hold until funding is found. What would it cost, and who would pay?
- CDOT prints a $10.9 million construction cost and a $12,421,478.23 contract value. What does each cover?
Total cost and spending
Total cost & funding are drawn from the official record(s) listed below.
Pacing
Money paid against contract time used, from CDOT's monthly dashboards for September 2026, the latest in the record. CALC
- Construction package 1 contract Paid 61.2% of the contract with 87.8% of its time used: 26.6 percentage points behind an even pace, $3.31M less.
An even pace is our baseline, not CDOT's plan. A gap is a question to ask, not a verdict, and it compares money with time, not with the work done.
See pacing month by monthMilestones (4)
- Construction manager/general contractor awarded for pre-construction — November 2023
- Construction package 1 began — July 2025
- Package 1 under way — through January 2027
- Package 2 start — to be determined
Who is being paid (1)
| Vendor | Contract / value | Paid to date | Confidence |
|---|---|---|---|
| WITHHELDCM/GC contract, Vasquez Boulevard (project 22922) | $12,421,478.23 contract | $7,597,382.84 paid · Sep 2026 | A |
Sources and receipts (2)
- ACDOT — Vasquez Boulevard Improvements project page: cost, timeline and contractor (codot.gov)read 25 September 2026
- ACDOT — Vasquez Boulevard Improvements monthly project dashboard (September 2026)read 26 September 2026