CDOT · Transportation
Vasquez Boulevard Improvements: I-270 to 64th Avenue
Lane, median, signal and intersection work on Vasquez Boulevard in Commerce City, the first of two scheduled construction packages (Adams County). Timeline Jul 2025–Jan 2027.
Updated Oct 13
Copy this address:
Underway. What this stage means
Underway. The main work on this project started. Money goes out as the work goes on.
The stages, in order
- Requested An agency asked. No money yet.
- Funded Money approved. Work still to start.
- Underway Work started. Money goes out. This project
- Complete Work complete.
Halted Work stopped before the end.
This stage is our reading of the sources at the foot of this page, last read 26 September 2026.
Timeline Jul 2025–Jan 2027
CDOT’s dashboard prints this for one contract, not for the whole project. Printed: $7,597,382.84. Who is being paid
Your take on this project
A rating here is not a vote, a scientific poll or a message to your representative.
Your rating is kept with no name, and it is never published on this site.
How we use this
Latest public update
CDOT's project page prints a Construction Cost of $10.9 million for package 1 on Vasquez Boulevard. The package runs from mile point 293 to 293.7 in Commerce City, with work from July 2025 to January 2027. CDOT's September 2026 dashboard prints $7,597,382.84 paid to date and $4,824,095.39 remaining on a current contract value of $12,421,478.23. That is the one construction manager/general contractor contract the dashboard reports on. Its value and the page's construction cost are different figures, and this site does not add or reconcile them. CDOT's page says package 2 was expected to begin in early 2026 and package 3 is on hold until further funding is obtained.
Related project: I-270 Corridor Improvements. A separate CDOT project on the interstate this road meets. The I-270 Corridor Improvements rebuild the Vasquez Boulevard/I-270 interchange in Phase 2 and the Vasquez Boulevard bridge over Sand Creek in Phase 3. Each project's figures are its own, and this site does not add them together.
Open questions for the state (2)
- Package 3 is on hold until funding is found. What would it cost, and who would pay?
- CDOT prints a $10.9 million construction cost and a $12,421,478.23 contract value. What does each cover?
Total cost and spending
The publisher prints this as a construction cost, not as the whole project’s cost, and prints no project total. It is drawn from the official record(s) listed below.
Milestones (4)
- Construction manager/general contractor awarded for pre-construction — November 2023
- Construction package 1 began — July 2025
- Package 1 under way — through January 2027
- Package 2 start — to be determined
Who is being paid (1)
| Political giving | |||||
|---|---|---|---|---|---|
| Jalisco InternationalCM/GC contract, Vasquez Boulevard (project 22922) | $12,421,478.23 contract | $7,597,382.84 paid · Sep 2026 | A | CDOT project page | Search TRACER |
Pacing CALC
Is the money keeping pace with the calendar?
Construction package 1 contract, September 2026
▼ −26.6 percentage points, paid behind the calendar
An even pace is our baseline, not CDOT's plan. A gap is a question to ask, not a verdict, and it compares money with time, not with the work done.
See the spending in detailMoney paid against contract time used, from CDOT's monthly dashboards for September 2026, the latest in the record.
- Construction package 1 contract Paid 61.2% of the contract with 87.8% of its time used: 26.6 percentage points behind an even pace, $3.31M less.
Sources and receipts (2)
- ACDOT — Vasquez Boulevard Improvements project page: cost, timeline and contractor (codot.gov)read 25 September 2026
- ACDOT — Vasquez Boulevard Improvements monthly project dashboard (September 2026)read 26 September 2026