I-270 Corridor Improvements
Rebuild of I-270 between I-25 and I-70, mile points 1 to 5: one tolled Express Lane each way beside two general-purpose lanes, 12 aging bridges replaced and the Vasquez Boulevard interchange rebuilt (Adams and Denver counties). Timeline Oct 2026–2033.
Copy this address:
Underway. What this stage means
Underway. The main work on this project started. Money goes out as the work goes on.
The stages, in order
- Requested An agency asked. No money yet.
- Funded Money approved. Work still to start.
- Underway Work started. Money goes out. This project
- Complete Work complete.
Halted Work stopped before the end.
This stage is our reading of the sources at the foot of this page, last read 20 October 2026.
Timeline Oct 2026–2033
CDOT’s dashboard prints this for one contract, not for the whole project. Printed: $11.97M. Who is being paid
Your take on this project
A rating here is not a vote, a scientific poll or a message to your representative.
Your rating is kept with no name, and it is never published on this site.
How we use this
Latest public update
Construction is under way. CDOT's project page, read on 20 October 2026, prints a Construction Cost of $806 million and a timeline of October 2026 to 2033. The combined Final Environmental Impact Statement and Record of Decision was signed on 20 August 2026. The project replaces 12 bridges built in the 1960s and adds one tolled Express Lane each way beside two general-purpose lanes. CDOT has published no release dating the start of construction, so this site gives none. The Record of Decision lists three phase costs as of April 2026, $307 million, $402 million and $97 million, and says they cover environmental review, design, construction and past bridge repair. Those three add to $806 million ($307M + $402M + $97M), the figure the project page calls a construction cost. Before the decision, the figures in public were estimates of the whole project's cost: $800 million in the regional transportation plan of May 2024, as the Record of Decision records it, and $725 million in coverage of the November 2025 Draft EIS. They were made on a different basis from the $806 million, so this site computes no change between them. CDOT's newest Critical Bridges dashboard is still the July 2026 edition: $11.97M paid to date and $9.86M remaining on a current contract value of $21.83M, for one pre-construction contract inside the project. This site does not add it to the $806 million.
Related project: Vasquez Boulevard Improvements: I-270 to 64th Avenue. A separate CDOT project on Vasquez Boulevard, from I-270 to 64th Avenue in Commerce City. This project rebuilds the Vasquez Boulevard/I-270 interchange in Phase 2 and the Vasquez Boulevard bridge over Sand Creek in Phase 3. Each project's figures are its own, and this site does not add them together.
Open questions for the state (3)
- CDOT's project page calls the $806 million a construction cost. Its Record of Decision says the same phase costs cover environmental review, design and past bridge repair too. Which is it?
- How will Phases 2 and 3 be paid for, and what share will Express Lane tolls carry?
- When will CDOT publish a monthly dashboard for the Phase 1 construction contract?
Total cost and spending
The publisher prints this as a construction cost, not as the whole project’s cost, and prints no project total. It is drawn from the official record(s) listed below.
Milestones (6)
- Corridor study & alternatives analysis — 2021–24
- Draft Environmental Impact Statement published — November 2025
- Final Environmental Impact Statement and Record of Decision approved — August 2026
- Phase 1 under way: embankment, eight of the 12 bridges, and the mainline from the South Platte River to the Vasquez Boulevard ramps — October 2026 to early 2030
- Phase 2: the rest of the mainline, the Vasquez Boulevard/I-270 interchange, and the York Street and 56th Avenue bridges — early 2030 to 2033
- Phase 3: the Vasquez Boulevard bridge over Sand Creek, Sandcreek Drive/Frontage Road, and a new bike and pedestrian overpass — early 2030 to 2033
Who is being paid (4)
| Political giving | |||||
|---|---|---|---|---|---|
| AtkinsRéalisLead NEPA/EIS consultant & design engineering services | — | PENDING Not published for this contract. | A | DEIS List of Preparers | Search TRACER |
| Felsburg Holt & UllevigEIS subconsultant (listed preparer) | — | PENDING Not published for this contract. | A | DEIS List of Preparers | Search TRACER |
| Kiewit Infrastructure Co.Critical Bridges pre-construction contract (project 24947/24527) | $21.83M contract | $11.97M paid · Jul 2026 | A | CDOT CM award recommendation memo (Mar 2023) | Search TRACER |
| Kiewit CorporationConstruction contractor named on CDOT's project page | — | PENDING Not published for this contract. | A | CDOT project page | Search TRACER |
Pacing CALC
Is the money keeping pace with the calendar?
I-270 Critical Bridges, pre-construction contract, July 2026
▼ −30.3 percentage points, paid behind the calendar
An even pace is our baseline, not CDOT's plan. A gap is a question to ask, not a verdict, and it compares money with time, not with the work done.
See the spending in detailMoney paid against contract time used, from CDOT's monthly dashboards for July 2026, the latest in the record.
- I-270 Critical Bridges, pre-construction contract Paid 54.8% of the contract with 85.1% of its time used: 30.3 percentage points behind an even pace, $6.61M less.
Figures in CDOT’s dashboards that do not add up
These are CDOT’s own figures, shown exactly as CDOT printed them, and we do not say which one is right.
-
Change orders do not add up CALC
I-270 Critical Bridges, July 2026
CDOT’s dashboard for this month prints:
- Initial Pre-Construction Contract's Value: $10.51 Million
- Total Change Orders to Date: $10.51 Million
- Current Contract's Value: $21.83 Million
Those two add up to $21.02M. That is $0.81M less than the current value.
$10.51M + $10.51M = $21.02M; $21.83M − $21.02M = $0.81MCDOT’s dashboard, July 2026 (PDF) (opens in a new tab) · read 26 September 2026
None of these figures is used in a total, a chart or the pacing view on this site.
Sources and receipts (5)
- ACDOT — I-270 Corridor Improvements project page: cost, timeline and contractor (codot.gov)read 20 October 2026
- ACDOT and FHWA — I-270 Record of Decision, signature page (Aug 2026)read 20 October 2026
- ACDOT and FHWA — I-270 Record of Decision, Chapter 7: phasing, funding and costs (Aug 2026)read 20 October 2026
- BColorado Sun — I-270 rebuild & widening coverage (Nov 2025)read 24 September 2026
- ACDOT — I-270 Critical Bridges project dashboard (July 2026)read 20 October 2026