CDOTI-270 Corridor Improvements
All projects
FACT B Honesty Framework The label says how we know the figure. The grade rates the source record, not the project. The grade rates the source record, not the project.

CDOT · Transportation

I-270 Corridor Improvements

Rebuild & widening of 7 mi of I-270 between I-76 and I-70: one managed lane each way, eight bridge replacements (Adams County). Timeline EIS 2025-26 · constr. TBD.

Est. total cost
≈ $725M
Delivery stage
○ Funded
Paid so far, to whom PENDING

Your take on this project

Latest public update

CDOT's preferred alternative adds one managed express lane in each direction and rebuilds eight deteriorating bridges; the current estimate is ≈ $725M (earlier coverage cited ≈ $800M).

Open questions for the state ANALYSIS

  • How will the ≈ $725M be financed — and what share comes from tolling?
  • What happens to cost and scope if the record of decision slips past 2027?

Fiscal position

Total project cost≈ $725M

Total cost & funding are drawn from the official record(s) listed below.

Spend-to-date: not published. Colorado does not publish what it has spent on this project, so this field is left blank rather than estimated. It will fill from TOPS/CORE vendor expenditure data as payments are matched to projects.

Milestones

  • Corridor study & alternatives analysis — 2021–24
  • Draft Environmental Impact Statement published — November 2025
  • Record of decision & final design — expected 2026–27
  • Construction start — TBD

Estimate, first to current FACT

first public estimate → current−$75M · −9%
2024 press coverage → 2025 DEIS estimate$800M → $725M
Watchlist average drift+50% per project · +23% dollar-weighted
Both endpoints are drawn from the source records below; the change, percentage, and average are our arithmetic (CALC). The average covers the 5 of 50 tracked projects with two published estimates — for the rest, the state has published a single figure, so their drift is unknowable, not zero. Estimates move in both directions — we show the honest record either way.

Who is being paid FACT

Funding sourceCDOT 10-Year Plan; full financing plan pending the record of decision.
VendorContract / valuePaid to dateConfidence
WITHHELDLead NEPA/EIS consultant & design engineering services—PENDINGA
WITHHELDEIS subconsultant (listed preparer)—PENDINGA
The money is published; the names are held. Each row below carries the contract value, what has been paid to date so far as it is published, and our confidence grade — the same figures as always, from the same official records. What is withheld is the vendor's name, the record link that names it, and the campaign-finance search that sat beside it. That is a deliberate decision taken pending legal review, not a figure we could not find: a blank cell would have said the opposite. What WITHHELD means

Source records

Follow this project

I-270 Corridor Improvements

Point a phone camera at this to open the project.