COLORADO WORKS BETTER™ Taxpayer Shareholder Portal Follow

Who runs this

Works Better Corporation, a nonpartisan public benefit corporation, builds this site.

Independent public-records project, separate from the State of Colorado and from every party and campaign.

Every number carries one of four labels (FACT, CALC, SAMPLE or PENDING) and a source you can open.

← US 6 Elk Creek Bridge Replacement in New Castle

US 6 Elk Creek Bridge Replacement in New Castle · Pacing

Is the money keeping pace with the calendar?

CDOT posts a monthly dashboard for one US 6 Elk Creek Bridge Replacement in New Castle contract, and only that one. The card puts two of its figures side by side: the share of contract time used and the share of the contract value paid.

Source: CDOT, US 6 Elk Creek Bridge Replacement in New Castle project dashboards (opens in a new tab) · 1 monthly document · October 2026

One month in: history starts now

CDOT's dashboard for October 2026 is the first one we have for this project, so there is no line to draw yet. Each month that follows adds a point. CDOT dashboard, October 2026 (opens in a new tab)

Bridge replacement contract

Contract 24493
Time used CALC77.6%
Paid CALC62.3%

Paid 62.3% of the contract with 77.6% of its time used: 15.4 percentage points behind an even pace, $1.62M less.

▼ Paid behind the calendar

$6.57M paid of $10.55M FACT · 330 of 425 days

How these numbers are made

Labels

  • FACT printed on CDOT's monthly dashboard for that contract and month. The link above the cards opens that document.
  • CALC our arithmetic on those figures, with the formula stated here.

Formulas

  • Time used % = days elapsed ÷ days total, both as CDOT prints them.
  • Paid % = payments to date ÷ current contract value.
  • Gap, in percentage points = paid % − time used %. It is a difference of two percentages, so it is in percentage points, not percent. Above zero, the contract is paid ahead of the calendar (▲). Below zero, it is paid behind the calendar (▼).
  • Gap, in dollars = payments to date − time used % × contract value. It is how far payments sit from what an even pace would have paid by then.
  • An even pace is our baseline, not CDOT's plan. It assumes the money is paid at the same rate as the contract's days pass. CDOT does not publish an expected spending curve for these contracts. Construction spending rarely keeps a steady rate: mobilization and early materials run ahead, winter slows work, closeout runs behind, and retainage holds back part of each payment. So a gap either way is a question to ask, not a verdict. It compares money with time, never with the work done.

What this does not show

  • These are payments on each contract, not the whole cost of the project. Design outside these contracts, right of way and CDOT's own costs are in none of them.
  • Every figure on this page is read from 1 of CDOT's monthly dashboards, October 2026. None is typed by hand.