US 6 Elk Creek Bridge Replacement in New Castle
Replacement of the US 6 bridge over Elk Creek on the west end of New Castle, mile point 105.8 (Garfield County). Timeline Jan–Nov 2026.
Updated Oct 13
Copy this address:
Underway. What this stage means
Underway. The main work on this project started. Money goes out as the work goes on.
The stages, in order
- Requested An agency asked. No money yet.
- Funded Money approved. Work still to start.
- Underway Work started. Money goes out. This project
- Complete Work complete.
Halted Work stopped before the end.
This stage is our reading of the sources at the foot of this page, last read 3 October 2026.
Timeline Jan–Nov 2026
CDOT’s dashboard prints this for one contract, not for the whole project. Printed: $6.57M. Who is being paid
Your take on this project
A rating here is not a vote, a scientific poll or a message to your representative.
Your rating is kept with no name, and it is never published on this site.
How we use this
Latest public update
CDOT's project page prints a Construction Cost of $10 million for replacing the US 6 bridge over Elk Creek and expects the project to be complete by November 2026. CDOT's October 2026 dashboard prints $6.57M paid to date and $3.98M remaining on a current contract value of $10.55M. That is the one construction contract. Its value and the page's construction cost are two figures CDOT prints for different things, and this site adds neither to the other. CDOT's page names New Castle, which is in Garfield County, and tags the project Mesa County.
Open questions for the state (2)
- CDOT's page prints a $10 million construction cost and its October dashboard a $10.55M current contract value. What does each cover?
- The dashboard prints no change-order figure. What moved the contract from its $10.09M original amount to $10.55M?
Total cost and spending
The publisher prints this as a construction cost, not as the whole project’s cost, and prints no project total. It is drawn from the official record(s) listed below.
Milestones (4)
- Construction contract awarded — August 2023
- Notice to proceed #1 — September 2025
- Construction under way — through November 2026
- Project complete — November 2026
Who is being paid (1)
| Political giving | |||||
|---|---|---|---|---|---|
| R.L. WadsworthBridge replacement contract (project 24493) | $10.55M contract | $6.57M paid · Oct 2026 | A | CDOT project page | Search TRACER |
Pacing CALC
Is the money keeping pace with the calendar?
Bridge replacement contract, October 2026
▼ −15.4 percentage points, paid behind the calendar
An even pace is our baseline, not CDOT's plan. A gap is a question to ask, not a verdict, and it compares money with time, not with the work done.
See the spending in detailMoney paid against contract time used, from CDOT's monthly dashboards for October 2026, the latest in the record.
- Bridge replacement contract Paid 62.3% of the contract with 77.6% of its time used: 15.4 percentage points behind an even pace, $1.62M less.
Sources and receipts (2)
- ACDOT — US 6 Elk Creek Bridge Replacement project page: cost, timeline and contractor (codot.gov)read 25 September 2026
- ACDOT — US 6 Elk Creek monthly project dashboard (October 2026)read 3 October 2026