CDOTCO 119 Safety, Mobility & Bikeway
All projects

CDOT · Transportation

CO 119 Safety, Mobility & Bikeway

Safety, mobility and bikeway improvements on the Diagonal Highway between Boulder and Longmont, from about Foothills Parkway to Hover Street (Boulder County). Timeline Fall 2024–Spring 2027.

Money in FACT
Est. total cost
$165M
Result so far
Underway. What this stage means

Underway. The main work on this project started. Money goes out as the work goes on.

The stages, in order

  1. Requested An agency asked. No money yet.
  2. Funded Money approved. Work still to start.
  3. Underway Work started. Money goes out. This project
  4. Complete Work complete.

Halted Work stopped before the end.

This stage is our reading of the sources at the foot of this page, last read 14 November 2026.

Timeline Fall 2024–Spring 2027

Paid so far CALC
$82.92M, through October 2026

CDOT’s dashboards print a paid figure for all two of this project’s contracts. Our sum: $70.82M + $12.10M = $82.92M. CDOT prints no total. Who is being paid, contract by contract

FACT A Honesty Framework The label says how we know the figure. The grade rates the source record, not the project. The grade rates the source record, not the project.

Your take on this project

How well does this project use public money?
Your rating and comment help show which projects residents see as a good use of public money, and which as a poor one.

A rating here is not a vote, a scientific poll or a message to your representative.

Your rating is kept with no name, and it is never published on this site.

How we use this
Your rating is stored without your name, address or any identifier. We count it into a total, so the people who govern this place can see how residents read their spending. No rating and no total is published on this site. We may publish summaries of what residents tell us about a place. Those are our own writing, never your rating and never a count, average or distribution of anybody's. Ratings and comments are grouped into themes that show elected leaders how residents rate each project.

Latest public update

CDOT's project page prints a Program Cost of $165 million for the CO 119 work between Boulder and Longmont, and a timeline of fall 2024 to spring 2027. CDOT's monthly dashboard for October 2026 reports two construction contracts: $82.92M paid to date against $96.91M in current contract value (our sums of the two contracts' printed figures). Those are payments on two contracts, not the project's whole cost, and this site does not add them to the $165 million. A third construction package, whose notice to proceed CDOT dates 3 September 2026, is not in these figures.

Open questions for the state (2)

  • CDOT prints a $165 million program cost and two construction contracts worth $96.91M. What else does the program include?
  • When will CDOT report payments on the third construction package?

Total cost and spending

Total project cost$165M

Total cost & funding are drawn from the official record(s) listed below.

Paid to contractors: $82.92M of $96.91M in current contracts. CALC CDOT’s monthly dashboards print what has been paid to the contractor to date on all two of this project’s contracts. The two totals are our sums of those figures: $70.82M + $12.10M = $82.92M, and $76.66M + $20.25M = $96.91M. They are payments on those contracts, not the project’s whole spend: anything paid outside them is in neither figure, and nobody publishes that. CDOT’s latest published dashboard: October 2026.

Milestones (3)

  • Construction began — September 2024
  • Construction under way, delivered as construction manager/general contractor — 2024–2027
  • Project timeline ends — Spring 2027

Who is being paid (2)

Funding sourceNot stated on CDOT's project page.
Major vendors on this project: contract value, amount paid so far and confidence grade, with a source record and a campaign-finance search link for each
Political giving
Kraemer North AmericaCM/GC contract, construction package 1 (project 25959)$76.66M contractACDOT project pageSearch TRACER
Kraemer North AmericaCM/GC contract, construction package 2 (project 25960)$20.25M contractACDOT project pageSearch TRACER
Where this comes from: award announcements and project records from CDOT, FHWA, agencies and the legislature’s nonpartisan staff — each Record link opens the source. Paid-to-date shows only published figures (green = verified); everything else stays PENDING, because the state does not publish payments project by project. Political giving links open TRACER, the Secretary of State’s official campaign-finance database, where contribution records are searchable by name — contributions are legal and public, and a search link implies no wrongdoing by anyone.

Pacing CALC

Is the money keeping pace with the calendar?

An even pace is our baseline, not CDOT's plan. A gap is a question to ask, not a verdict, and it compares money with time, not with the work done.

See the spending in detail

Money paid against contract time used, from CDOT's monthly dashboards for October 2026, the latest in the record.

  • Construction package 1 Paid 92.4% of the contract with 96.2% of its time used: 3.8 percentage points behind an even pace, $2.89M less.
  • Construction package 2 Paid 59.8% of the contract with 92.9% of its time used: 33.1 percentage points behind an even pace, $6.71M less.