CDOT · Transportation
CO 119 Safety, Mobility & Bikeway
Safety, mobility and bikeway improvements on the Diagonal Highway between Boulder and Longmont, from about Foothills Parkway to Hover Street (Boulder County). Timeline Fall 2024–Spring 2027.
Copy this address:
Underway. What this stage means
Underway. The main work on this project started. Money goes out as the work goes on.
The stages, in order
- Requested An agency asked. No money yet.
- Funded Money approved. Work still to start.
- Underway Work started. Money goes out. This project
- Complete Work complete.
Halted Work stopped before the end.
This stage is our reading of the sources at the foot of this page, last read 14 November 2026.
Timeline Fall 2024–Spring 2027
CDOT’s dashboards print a paid figure for all two of this project’s contracts. Our sum: $70.82M + $12.10M = $82.92M. CDOT prints no total. Who is being paid, contract by contract
Your take on this project
A rating here is not a vote, a scientific poll or a message to your representative.
Your rating is kept with no name, and it is never published on this site.
How we use this
Latest public update
CDOT's project page prints a Program Cost of $165 million for the CO 119 work between Boulder and Longmont, and a timeline of fall 2024 to spring 2027. CDOT's monthly dashboard for October 2026 reports two construction contracts: $82.92M paid to date against $96.91M in current contract value (our sums of the two contracts' printed figures). Those are payments on two contracts, not the project's whole cost, and this site does not add them to the $165 million. A third construction package, whose notice to proceed CDOT dates 3 September 2026, is not in these figures.
Open questions for the state (2)
- CDOT prints a $165 million program cost and two construction contracts worth $96.91M. What else does the program include?
- When will CDOT report payments on the third construction package?
Total cost and spending
Total cost & funding are drawn from the official record(s) listed below.
Milestones (3)
- Construction began — September 2024
- Construction under way, delivered as construction manager/general contractor — 2024–2027
- Project timeline ends — Spring 2027
Who is being paid (2)
| Political giving | |||||
|---|---|---|---|---|---|
| Kraemer North AmericaCM/GC contract, construction package 1 (project 25959) | $76.66M contract | $70.82M paid · Oct 2026 | A | CDOT project page | Search TRACER |
| Kraemer North AmericaCM/GC contract, construction package 2 (project 25960) | $20.25M contract | $12.10M paid · Oct 2026 | A | CDOT project page | Search TRACER |
Pacing CALC
Is the money keeping pace with the calendar?
An even pace is our baseline, not CDOT's plan. A gap is a question to ask, not a verdict, and it compares money with time, not with the work done.
See the spending in detailMoney paid against contract time used, from CDOT's monthly dashboards for October 2026, the latest in the record.
- Construction package 1 Paid 92.4% of the contract with 96.2% of its time used: 3.8 percentage points behind an even pace, $2.89M less.
- Construction package 2 Paid 59.8% of the contract with 92.9% of its time used: 33.1 percentage points behind an even pace, $6.71M less.
Sources and receipts (2)
- ACDOT — CO 119 Safety, Mobility & Bikeway project page: cost, timeline and contractor (codot.gov)read 25 September 2026
- ACDOT — CO 119 monthly project dashboard (October 2026)PENDING no link on fileread 14 November 2026