← Capitol Complex Renovation, Phase 3/4

Capitol Complex Renovation, Phase 3/4 · Budget to actual

How much of the budget can a public record show was paid?

A budget names this project. A payment record names a contract, a fund or a vendor. This page links the two, one record at a time, and grades each link by how sure it is. Money no public record ties to the project stays unlinked. We never guess it.

Budget basis FACT
$96,187,757
Appropriated to the project before FY 2026-27, all cash funds from the Capitol Complex Renovation Fund
Linked payments CALC
$88,898,708
92.4% of the basis
Unlinked CALC
$7,289,049
Not tied to this project by any public record yet. This is not the same as unspent.
  • Documented $88,898,708 92.4% of the basis

Budgeted and allocated

Every public figure for what this project was given or is expected to cost. The basis is the one the linked payments are measured against. Other lines are shown and not added.

Budget figures for Capitol Complex Renovation, Phase 3/4, with label and source
What it isAmountLabelSource
Estimated total cost of the Capitol Complex Renovation and Footprint Reduction project, all four phasesEstimated total cost of the whole project $216,700,000 FACT Joint Budget Committee staff, FY 2026-27 Capital Construction figure setting (opens in a new tab), page 17. As of February 25, 2026.
Appropriated to the project before FY 2026-27, all cash funds from the Capitol Complex Renovation Fund The basisMoney appropriated to date, summed by the publisher $96,187,757 FACT Department of Personnel and Administration, FY 2026-27 Capital Construction Request (to the Capital Development Committee) (opens in a new tab), page 1. As of December 9, 2025.
Part of the basis. FY 2022-23 appropriation, S.B. 22-239Money a legislature appropriated $26,721,314 FACT Session Laws 2022, chapter 411 (S.B. 22-239, Buildings in the Capitol Complex) (opens in a new tab), page 6. As of June 7, 2022.
Part of the basis. FY 2023-24 appropriation, S.B. 23-306Money a legislature appropriated $20,479,729 FACT Session Laws 2023, chapter 412 (S.B. 23-306, Buildings in the Capitol Complex) (opens in a new tab), page 6. As of June 6, 2023.
Part of the basis. FY 2023-24 appropriation, S.B. 23-214 (the Long Bill)Money a legislature appropriated $14,759,883 FACT Session Laws 2023, chapter 474 (S.B. 23-214, the FY 2023-24 Long Bill) (opens in a new tab), page 335. As of May 1, 2023.
Part of the basis. FY 2024-25 appropriation, H.B. 24-1430 (the Long Bill)Money a legislature appropriated $18,179,092 FACT Session Laws 2024, chapter 519 (H.B. 24-1430, the FY 2024-25 Long Bill) (opens in a new tab), page 361. As of May 1, 2024.
Part of the basis. FY 2025-26 appropriation, S.B. 25-206 (the Long Bill)Money a legislature appropriated $16,047,739 FACT S.B. 25-206, the FY 2025-26 Long Bill, capital construction section, page 9. As of April 24, 2025.
FY 2026-27 request for phase 3/4, cash funds from the Capitol Complex Renovation Fund, recommended for denial by JBC staffMoney requested and not appropriated $41,450,138 FACT Joint Budget Committee staff, FY 2026-27 Capital Construction figure setting (opens in a new tab), page 7. As of February 25, 2026.
Moved out of the Capitol Complex Renovation Fund to the General Fund on June 30, 2026, by H.B. 26-1406Money moved out of the project’s fund by law $15,263,000 FACT Session Laws 2026, chapter 286 (H.B. 26-1406, Repeal Capital Construction Funding Requirements) (opens in a new tab), page 1. As of June 1, 2026.

Also published, not added

Other public figures for the same money. Each is shown so you can check it, and none is added, so nothing is counted twice.

What cannot be bridged, and why

  • Which of the four phases each payment paid for. TOPS has no project, phase or contract field. JBC staff write that the phases overlap and draw from several appropriation years, and that this makes them hard to track.
  • Payments from the General Fund or other funds for this project. Only the Capitol Complex Renovation Fund is named for the project. A payment from any other fund cannot be tied to it without a contract or project number, which TOPS does not publish.
  • Money owed but not yet paid. TOPS is cash paid. Encumbrances and contract balances are not published.
  • How much of the gap between appropriated and paid is unspent, owed or swept. Appropriations stay available for two more years. The law that swept $15,263,000 from the fund in June 2026 does not say which appropriation year it came from, and no public report prints the fund's balance by year.

How this works

Link grades

  • Exact The publisher prints the same key on both records, such as a contract code.
  • Documented A public document states in words that this money belongs to this project.
  • Inferred Our own match, by name, place or date. It is our arithmetic, and the method is shown.
  • Pending No public record links this money to the project yet. It moves no dollars.

Formulas

  • Linked payments = the sum of every Exact, Documented and Inferred link. A Pending link adds nothing.
  • Unlinked = the basis − linked payments.
  • Share = linked payments ÷ the basis.
  • A link never moves more than the payment record it comes from states, and the linked total never passes the basis. Our checks fail the page if either happens.

What this does not show

  • Unlinked money is not unspent money. It is money no public record ties to this project yet.
  • A contractor is named as the contractor of record.