DPA · Buildings & facilities
Capitol Complex Renovation, Phase 3/4
Renovation & footprint reduction of the state legislative/office complex. Denver County. Timeline FY 2026-27 (multi-yr).
Copy this address:
Underway. What this stage means
Underway. The main work on this project started. Money goes out as the work goes on.
The stages, in order
- Requested An agency asked. No money yet.
- Funded Money approved. Work still to start.
- Underway Work started. Money goes out. This project
- Complete Work complete.
Halted Work stopped before the end.
This stage is our reading of the sources at the foot of this page, last read 24 September 2026.
Timeline FY 2026-27 (multi-yr)
Colorado does not publish what it has spent on this project.
Your take on this project
A rating here is not a vote, a scientific poll or a message to your representative.
Your rating is kept with no name, and it is never published on this site.
How we use this
Latest public update
The ≈ $216.7M is the whole project, and the document that states it is the Joint Budget Committee’s FY 2026-27 capital figure-setting document, page 15: “The total cost of the project is currently estimated at $216.7 million, with an unfunded $31.7 million General Fund cost.” The same page records $96.2M already appropriated from FY 2022-23 through FY 2025-26. The FY 2026-27 phase-3 request of $41.5M (cash funds) was recommended for denial by JBC staff and does not appear in the enacted Long Bill capital schedule; earlier phases continue, and the operating budget carries $16.8M/yr in Capitol Complex facilities maintenance.
Open questions for the state (1)
- What annual operating savings does the footprint reduction target?
Total cost and spending
Total cost & funding are drawn from the official record(s) listed below.
Budget to actual
Public records tie $88,898,708 of payments to this project. That is 92.4% of the $96,187,757 basis: appropriated to the project before FY 2026-27, all cash funds from the Capitol Complex Renovation Fund.
- Documented $88,898,708 92.4% of the basis
Each link is graded by how sure the record is. The other $7,289,049 is unlinked. Some of it may be unspent, and some may be paid where no public record names this project.
See every link and its evidenceMilestones (3)
- Phases 1–2 — prior years
- Phase 3 — FY 2026-27
- Phase 4 — FY 2028-29
Who is being paid (1)
| Political giving | |||||
|---|---|---|---|---|---|
| Fransen Pittman ConstructionGeneral contractor — Capitol Annex renovation (phase 1) | ≈ $47M (Annex) | PENDING Not published for this contract. | B | Colorado Politics (Nov 2025) | Search TRACER |
Sources and receipts (2)
- BJBC — FY 2026-27 Capital Construction figure-settingread 24 September 2026
- AHB26-1410 — enacted Long Bill (FY 2026-27)read 24 September 2026