CDOT · Transportation
I-70 West Vail Pass Auxiliary Lanes
Auxiliary lanes, new bridges, wildlife crossings & rockfall mitigation (10 mi, Eagle County). Timeline 2021–2026.
Copy this address:
CALC Up 97.9% from $164.2M.
Formula: ($325M − $164.2M) ÷ $164.2M. First figure: CDOT, first-phase project (INFRA award).
Underway. What this stage means
Underway. The main work on this project started. Money goes out as the work goes on.
The stages, in order
- Requested An agency asked. No money yet.
- Funded Money approved. Work still to start.
- Underway Work started. Money goes out. This project
- Complete Work complete.
Halted Work stopped before the end.
This stage is our reading of the sources at the foot of this page, last read 24 September 2026.
Timeline 2021–2026
Colorado does not publish what it has spent on this project.
Your take on this project
A rating here is not a vote, a scientific poll or a message to your representative.
Your rating is kept with no name, and it is never published on this site.
How we use this
Latest public update
CDOT's construction page for the project gives its construction cost as $325M, with a timeline of August 2021 to December 2026 and substantial completion scheduled by December 2026. CDOT's main project page still describes the $164.2M project it started with a $60.7M federal INFRA grant as the first phase; CDOT does not say how the scope moved between the two figures. Until 24 September 2026 this row showed ≈ $200M, taken from press coverage while the two figures were unreconciled.
Open questions for the state (1)
- What is the audited final cost once the corridor is complete?
Total cost and spending
Total cost & funding are drawn from the official record(s) listed below.
Budget to actual
Public records tie $207,103,126 of payments to this project. That is 63.7% of the $325,000,000 basis: construction cost, as CDOT's construction page states it (August 2021 to December 2026).
- Exact $93,598,472 28.8% of the basis
- Documented $113,504,654 34.9% of the basis
Each link is graded by how sure the record is. The other $117,896,874 is unlinked. Some of it may be unspent, and some may be paid where no public record names this project.
See every link and its evidenceMilestones (3)
- Construction began — 2021
- Final construction season — 2026
- Completion — end 2026
Estimate, first to current
Who is being paid (2)
| Political giving | |||||
|---|---|---|---|---|---|
| Kiewit Infrastructure Co.CM/GC construction contractor | — | PENDING Not published for this contract. | A | CDOT construction-phase page | Search TRACER |
| RS&H, Inc.Prime design consultant | — | PENDING Not published for this contract. | B | trade press / firm page | Search TRACER |
Sources and receipts (2)
- ACDOT — I-70 West Vail Pass construction pageread 24 September 2026
- ACDOT — I-70 West Vail Pass project pageread 24 September 2026