I-70 West Vail Pass Auxiliary Lanes

Auxiliary lanes, new bridges, wildlife crossings & rockfall mitigation (10 mi, Eagle County). Timeline 2021–2026.

Est. total cost
$325M
Delivery stage
● Underway
Paid so far, to whom PENDING

Your take on this project

Latest public update

CDOT's construction page for the project gives its construction cost as $325M, with a timeline of August 2021 to December 2026 and substantial completion scheduled by December 2026. CDOT's main project page still describes the $164.2M project it started with a $60.7M federal INFRA grant as the first phase; CDOT does not say how the scope moved between the two figures. Until 24 September 2026 this row showed ≈ $200M, taken from press coverage while the two figures were unreconciled.

Open questions for the state ANALYSIS

  • What is the audited final cost once the corridor is complete?

Fiscal position

Total project cost$325M

Total cost & funding are drawn from the official record(s) listed below.

Spend-to-date: not published. Colorado does not publish what it has spent on this project, so this field is left blank rather than estimated. It will fill from TOPS/CORE vendor expenditure data as payments are matched to projects.

Milestones

  • Construction began — 2021
  • Final construction season — 2026
  • Completion — end 2026

Estimate, first to current FACT

first public estimate → current+$160.8M · +98%
CDOT, first-phase project (INFRA award) → CDOT, construction cost (2026)$164.2M → $325M
Watchlist average drift+50% per project · +23% dollar-weighted
Both endpoints are drawn from the source records below; the change, percentage, and average are our arithmetic (CALC). The average covers the 5 of 50 tracked projects with two published estimates — for the rest, the state has published a single figure, so their drift is unknowable, not zero. Estimates move in both directions — we show the honest record either way.

Who is being paid FACT

Funding sourceState (SB 267 / Transportation Commission) with federal grants.
VendorContract / valuePaid to dateConfidence
WITHHELDCM/GC construction contractor—PENDINGA
WITHHELDPrime design consultant—PENDINGB
The money is published; the names are held. Each row below carries the contract value, what has been paid to date so far as it is published, and our confidence grade — the same figures as always, from the same official records. What is withheld is the vendor's name, the record link that names it, and the campaign-finance search that sat beside it. That is a deliberate decision taken pending legal review, not a figure we could not find: a blank cell would have said the opposite. What WITHHELD means

Source records

Follow this project

I-70 West Vail Pass Auxiliary Lanes

Point a phone camera at this to open the project.