I-25 South Gap: Monument to Castle Rock
18-mi widening, express lanes, five rebuilt bridges, wildlife crossings. Timeline 2018–2022.
Copy this address:
Est. total cost
$419M
Delivery stage
✓ Complete
Your take on this project
Latest public update
Completed November 2022 after roughly four years of construction.
Open questions for the state ANALYSIS
- Have the new wildlife crossings reduced vehicle–animal collisions as projected?
Fiscal position
Total project cost$419M
Total cost & funding are drawn from the official record(s) listed below.
Delivered. Project reported complete, so final spend approximates the total cost. Line-item expenditures can still be reconciled from TOPS/CORE.
Milestones
- Construction began — September 2018
- Express lanes open — 2022
- Project completed — November 2022
Who is being paid FACT
Funding sourceDouglas County, El Paso County, Pikes Peak Rural Transportation Authority, and a federal INFRA grant.
| Vendor | Contract / value | Paid to date | Confidence |
|---|---|---|---|
| WITHHELDCM/GC — construction contract announced August 2018 | $350M constr. | $419M project total · within budget | A |
The money is published; the names are held. Each row below carries the contract value, what has been paid to date so far as it is published, and our confidence grade — the same figures as always, from the same official records. What is withheld is the vendor's name, the record link that names it, and the campaign-finance search that sat beside it. That is a deliberate decision taken pending legal review, not a figure we could not find: a blank cell would have said the opposite. What WITHHELD means
Source records
- ACDOT — I-25 South Gap project page (codot.gov)read 24 September 2026