Renovation of the historic Guggenheim geography building. Timeline requested FY27.
Copy this address:
Est. total cost
$5.0M
Delivery stage
◌ Requested
Paid so far, to whom
Nothing. Not funded, so no contract exists.
Your take on this project
Latest public update
Requested at <b>$5,022,196</b> for FY 2026-27; the Capital Development Committee did not recommend funding it, and the project remains on the prioritized waitlist. The same request carries a further <b>$19,200,888</b> of FY 2027-28 cost, which is a separate year and is not added here — see the correction logged 17 Aug.
Open questions for the state ANALYSIS
- Where does this project sit on the CDC's prioritized waitlist, and what is deferral costing?
Fiscal position
Total project cost$5.0M
Total cost & funding are drawn from the official record(s) listed below.
Not funded. This project was requested in the FY 2026-27 budget cycle and is not in the enacted capital budget. It sits on the state's prioritized waitlist — no spending is expected unless a future budget funds it.
Milestones
- Requested in the FY 2026-27 budget cycle — not funded
- On the state's prioritized waitlist for a future budget year
Who is being paid
Funding sourceRequested from the Capital Construction Fund.
Not funded — no contracts exist for this project. If a future budget funds it, prime contracts will appear here from the Colorado Contract Management System.
Source records
- AJBC — FY 2026-27 Capital Construction Figure Setting (25 Feb 2026), CDC row 33read 24 September 2026