CPW · Buildings & facilities
Parks & Wildlife — Infrastructure & Real Property Maintenance
Dams, hatcheries, roads and facility repairs across CPW properties, statewide (capital renewal). Statewide. Timeline FY 2026-27.
Copy this address:
Funded. What this stage means
Funded. The state approved or set aside money for this project. The main work is still to start.
The stages, in order
- Requested An agency asked. No money yet.
- Funded Money approved. Work still to start. This project
- Underway Work started. Money goes out.
- Complete Work complete.
Halted Work stopped before the end.
This stage is our reading of the sources at the foot of this page, last read 24 September 2026.
Timeline FY 2026-27
Colorado does not publish what it has spent on this project.
Your take on this project
A rating here is not a vote, a scientific poll or a message to your representative.
Your rating is kept with no name, and it is never published on this site.
How we use this
Latest public update
Enacted at $11,293,800 in HB26-1410 Section 3 — capital renewal across CPW's dams, hatcheries and properties, funded by license fees rather than the General Fund.
Open questions for the state (1)
- What is CPW's deferred-maintenance backlog, and how far does $11.3M go against it?
Total cost and spending
Total cost & funding are drawn from the official record(s) listed below.
Milestones (2)
- Enacted in HB26-1410 Section 3, Part II (capital renewal)
- Project-level allocation — determined by CPW during the year
Who is being paid
Sources and receipts (1)
- AHB26-1410 — enacted Long Bill (FY 2026-27)read 24 September 2026