CO Mental Health Institute at Pueblo — Campus Utility Infrastructure
Water/sewer, fire hydrants, roadway & parking renewal (multi-phase). Pueblo County. Timeline multi-phase → FY 2029.
Copy this address:
Underway. What this stage means
Underway. The main work on this project started. Money goes out as the work goes on.
The stages, in order
- Requested An agency asked. No money yet.
- Funded Money approved. Work still to start.
- Underway Work started. Money goes out. This project
- Complete Work complete.
Halted Work stopped before the end.
This stage is our reading of the sources at the foot of this page, last read 24 September 2026.
Timeline multi-phase → FY 2029
Colorado does not publish what it has spent on this project.
Your take on this project
A rating here is not a vote, a scientific poll or a message to your representative.
Your rating is kept with no name, and it is never published on this site.
How we use this
Latest public update
Phase 2 funded: $4,144,206 enacted in HB26-1410 Section 3 for FY 2026-27; multi-phase program ≈ $34.7M. Context: CMHIP's operating budget is $160.0M/yr with 1,063 staff, and the state pays $12.8M/yr in consent-decree fines tied to competency-service delays at this system.
Open questions for the state (1)
- What is the full multi-phase cost and completion timeline?
Total cost and spending
Total cost & funding are drawn from the official record(s) listed below.
Milestones (2)
- Construction underway — current
- Remaining phases — through FY 2028-29
Who is being paid
Sources and receipts (2)
- BJBC — FY 2026-27 Capital Construction figure-settingread 24 September 2026
- BBHA — CMHIP construction announcementPENDING no link on filedated 2026