CDHSCO Mental Health Institute at Pueblo — Campus Utility Infrastructure
All projects
FACT B Honesty Framework The label says how we know the figure. The grade rates the source record, not the project. The grade rates the source record, not the project.

CDHS · Buildings & facilities

CO Mental Health Institute at Pueblo — Campus Utility Infrastructure

Water/sewer, fire hydrants, roadway & parking renewal (multi-phase). Timeline multi-phase → FY 2029.

Est. total cost
≈ $34.7M
Delivery stage
● Underway
Paid so far, to whom PENDING

Your take on this project

Latest public update

Phase 2 funded: $4,144,206 enacted in HB26-1410 Section 3 for FY 2026-27; multi-phase program ≈ $34.7M. Context: CMHIP's operating budget is $160.0M/yr with 1,063 staff, and the state pays $12.8M/yr in consent-decree fines tied to competency-service delays at this system.

Open questions for the state ANALYSIS

  • What is the full multi-phase cost and completion timeline?

Fiscal position

Total project cost≈ $34.7M

Total cost & funding are drawn from the official record(s) listed below.

Spend-to-date: not published. Colorado does not publish what it has spent on this project, so this field is left blank rather than estimated. It will fill from TOPS/CORE vendor expenditure data as payments are matched to projects.

Milestones

  • Construction underway — current
  • Remaining phases — through FY 2028-29

Who is being paid FACT

Funding sourceCapital Construction Fund (multi-phase capital budget).
No contractor publicly named — CDHS budget documents cite estimates from local contractors and engineers; procurement runs through state solicitation. Contract records pending CMS ingestion.