CSUCSU Clark Building Renovation & Addition
All projects
CALC B Honesty Framework The label says how we know the figure. The grade rates the source record, not the project. The grade rates the source record, not the project.

CSU · Buildings & facilities

CSU Clark Building Renovation & Addition

Four-phase renovation/expansion of CSU's largest classroom building. Timeline multi-phase → FY 2026-27.

Est. total cost
≈ $136.6M
Delivery stage
● Underway
Paid so far, to whom PENDING

Your take on this project

Latest public update

Phase 4 of 4 enacted at $25,798,175 in HB26-1410 Section 3 — the only new higher-education building project in the FY 2026-27 capital bill. The ≈ $136.6M program total is our arithmetic, and all three of its parts are stated together on page 8 of the Joint Budget Committee’s FY 2026-27 capital figure-setting document: previous Capital Construction Fund appropriations of $55.8M, $55.0M of CSU institutional funds, and this final phase. $55.8M + $55.0M + $25,798,175 = $136.6M. The institutional money is the university’s own and appears in no appropriation act, which is why no single act can carry this total.

Open questions for the state ANALYSIS

  • What is the projected completion date for the final phase?

Fiscal position

Total project cost≈ $136.6M

Total cost is our arithmetic on figures an official record states together: $55.8M + $55.0M + $25,798,175 ≈ $136.6M. Funding is drawn from the official record(s) listed below.

Spend-to-date: not published. Colorado does not publish what it has spent on this project, so this field is left blank rather than estimated. It will fill from TOPS/CORE vendor expenditure data as payments are matched to projects.

Milestones

  • Phases 1–3 — prior years
  • Phase 4/4 (final) — FY 2026-27

Who is being paid FACT

Funding source$55.8M Capital Construction Fund + $55.0M institutional + $25.8M final-phase appropriation.
VendorContract / valuePaid to dateConfidence
WITHHELDGeneral contractor (design-build team, selected December 2022)—PENDINGA
WITHHELDArchitect (design-build team)—PENDINGA
The money is published; the names are held. Each row below carries the contract value, what has been paid to date so far as it is published, and our confidence grade — the same figures as always, from the same official records. What is withheld is the vendor's name, the record link that names it, and the campaign-finance search that sat beside it. That is a deliberate decision taken pending legal review, not a figure we could not find: a blank cell would have said the opposite. What WITHHELD means

Source records